» Go to news mainCampus Construction Update
The Campus Construction Update is a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices during summer construction.
Week of May 29th
Piping installation to continue in Chute, Boulden, Ruminant Animal Centre, Langille buildings and start in Haley and Jenkins Hall Buildings. (chance of minor noise with this work)
Civil work for concrete pads in Chute, Boulden, Ruminant, Langille, Haley and Jenkins Hall Buildings.
Electrical work to begin in Haley building. (Chance of minor noise with this work, hammer drilling)
Week of June 5th
Piping installation to continue in Langille, Haley and Jenkins Hall Buildings. (chance of minor noise with this work)
Civil work for concrete pads in Chute, Boulden, Ruminant, Langille, Haley, and Jenkins Hall Buildings.
Electrical work to continue in Haley building. (Chance of minor noise with this work, hammer drilling)
Any questions or concerns please contact:
Stephanie MacKenzie
Project Manager Facilities Management
902.956.4492
Stephanie.Mackenzie@dal.ca
Recent News
- Chartwells Update
- Join the Residence Life team – Residence Life Don
- Rolling With Pride: ¹úÃñ²ÊƱ Faculty of Agriculture celebrates love, community, and color in the Truro Pride parade
- Romblon State University Summer Enrichment camp 2025 comes to a close
- We came. We mooed. We conquered.
- Learning, growing, belonging at Master Gardener Field School
- Celebrating Women in Engineering
- Living authentically in agriculture: Jon Raymond Dykstra’s story of pride and passion